Preliminary Cost Estimate


PRELIMINARY ENGINEER'S OPINION OF
PROBABLE CONSTRUCTION COSTS FOR PROPOSED BIKEPATH
 
September 11, 2007
   
Hunt Club Woods
Homer Glen, ILLINIOS
             PREPARED FOR:
            PREPARED BY: DesignTek Engineering, Inc.
9500 Bormet Drive, Suite 304
Mokena, Illinois 60448
This preliminary Engineer's Opinion of Probale Cunstruction Costs based on 750' of Bikepath, with no improvement plans in place.
Project Number: 07-0042
C:\Documents and Settings\peterb\Local Settings\Temp\[07-0042 Preliminary Cost Estimate-5.xls]Cost Estimate

Hunt Club Woods
Homer Glen, Illinois
PRELIMINARY ENGINEER'S OPINION OF
PROBABLE CONSTRUCTION COSTS FOR PROPOSED BIKEPATH
NO. ITEM UN QUANTITY UNIT COST TOTAL AMOUNT
GRADING        
1 Topsoil Excavation CY 417 $3.00 $1,250.00
2 Earth Excavation CY 113 $4.00 $453.33
3 Topsoil Respread (Disturbed Area) CY 278 $2.75 $763.89
4 Seeding AC 0.35 $3,750.00 $1,312.50
5 Silt Fence LF 1,500 $2.05 $3,075.00
TOTAL GRADING   $6,854.72
PAVING        
1 8" Agg. Base, CA-6, Type B SY 833 $5.25 $4,375.00
2 Bit. Mat'l, Prime Coat (0.30 gal/SY) GL 250 $1.50 $374.85
3 2" Bit. Conc. Surface Course, Cl. I SY 833 $4.50 $3,748.50
TOTAL PAVING   $8,498.35
STORM SEWER        
1 12" Dia. RCP LF 32 $18.50 $592.00
2 12" Conc.Flared End Section EA 2 $500.00 $1,000.00
3 Trench Backfill Material CY 4 $17.00 $68.00
TOTAL STORM SEWER $1,660.00
SUMMARY        
  GRADING       $6,854.72
  PAVING       $8,498.35
  STORM SEWER       $1,660.00
TOTAL   $17,013.07